02/02/08 - THIRD STREETSCAPE PLANNING MEETING
DDOT in consultation with Rhodeside and Harwell held an
open house on Saturday, February 2nd. The following documents were
reviewed by the Dupont Circle community.
01/16/08 -
DOCUMENTS SUBMITTED BY RHODESIDE AND HARWELL
12/06/07 - INITIAL DESIGN CONCEPTS PRESENTED BY
RHODESIDE AND HARWELL
10/22/07 - The District of
Columbia Department of Transportation (DDOT) began the Design Phase of a
17th Street Streetscape Project. The project covers 17th
Street from Massachusetts Avenue to New Hampshire Avenue, NW.
The 17th Street project will resurface the
street, sidewalks, curbs and gutters. The Dupont Circle community has the opportunity to address the
look of the 17th Street corridor by addressing the materials used and by our
choice of “street furniture” (utility poles, benches, garbage cans, PLANTERS,
etc), streetlights and street trees. We will also work on pedestrian safety,
traffic, parking and compliance with the Americans with Disability Act. T
DDOT hopes to launch the
construction phase project in the fall of 2008. The timeline for the project
includes:
1)
Three initial community meetings
before the end of January 2008 to create a concept design
2)
A meeting during the Design
Development phase, between February and April
3)
Construction documents between May
and July, with an information/community discussion regarding the construction
phase in approximately June, 2008. |